How Long Does It Take to Build a Custom Home in Nairobi?

A realistic timeline from concept to moving in


You’ve found the land. You’ve saved the money. You have sketches and dreams.

Now the question that every homeowner asks: How long will this actually take?

The honest answer? Longer than you hope. Shorter than you fear—if you do it right.

This guide breaks down the realistic timeline for building a custom home in Nairobi, phase by phase. No sugar-coating. No sales pitch. Just the facts you need to plan.


The Short Answer

For a typical 3-4 bedroom custom home in Nairobi:

PhaseDuration
Design & approvals4-8 months
Construction12-18 months
Finishing & handover1-2 months
Total18-28 months

From first client meeting to handing over the keys.

For a larger home (5+ bedrooms, high-end finishes): 24-36 months
For a simple developer house (replicated design): 8-12 months


Phase 1: Design & Approvals (4-8 Months)

This phase happens entirely before any construction begins. Rushing it guarantees problems later.

Step 1: Brief & Site Analysis (2-4 weeks)

Your architect visits your site, discusses your requirements, and develops an initial brief.

What happens:

  • Site survey and analysis
  • Discussion of rooms, layout, style
  • Initial budget discussion
  • Feasibility assessment

Deliverable: A clear project brief and initial concept directions.

Step 2: Concept Design (4-8 weeks)

The fun part. Your architect translates your brief into initial sketches and layouts.

What happens:

  • Floor plan options developed
  • Preliminary elevations and sections
  • Initial 3D visuals
  • Client feedback and iterations
  • Material and finish discussions

Deliverable: Approved concept design with floor plans and exterior visuals.

Step 3: Detailed Design & Technical Drawings (6-12 weeks)

The concept becomes a building that can actually be constructed.

What happens:

  • Detailed floor plans, elevations, sections
  • Structural engineering design
  • MEP (mechanical, electrical, plumbing) design
  • Material specifications
  • Window and door schedules
  • Kitchen and joinery details

Deliverable: Full set of construction drawings and specifications.

Step 4: Approvals (8-16 weeks)

This is where timelines stretch. Government approvals move at their own pace.

What happens:

  • County building permit application
  • NEMA approval (if required)
  • NCA project registration
  • Utility provider approvals
  • Addressing any plan queries

Deliverable: Approved stamped drawings and all regulatory clearances.

Pro tip: Factor in delays. Approvals rarely finish as fast as hoped.


Phase 2: Tender & Contractor Selection (4-8 Weeks)

With approved drawings, you’re ready to find a builder.

What happens:

  • Tender documents prepared
  • Invitations to qualified contractors
  • Bid review and analysis
  • Contractor interviews
  • Contract negotiation and signing

If using an integrated design-build team: This phase is greatly simplified or eliminated—you already have your builder.


Phase 3: Construction (12-18 Months)

This is where your home rises from the ground. The timeline varies significantly based on size, complexity, and weather.

Stage 1: Site Setup & Groundworks (4-8 weeks)

ActivityDuration
Site clearance and setup1-2 weeks
Setting out (marking building position)3-5 days
Excavation2-4 weeks
Foundation concrete2-3 weeks
Foundation curing2 weeks

Total: 4-8 weeks

Stage 2: Structure (16-24 weeks)

The skeleton of your home.

ActivityDuration
Ground floor slab2-3 weeks
Ground floor walls and columns4-6 weeks
First floor slab3-4 weeks
First floor walls4-6 weeks
Roof structure3-4 weeks
Roof covering2-3 weeks

Total: 16-24 weeks (4-6 months)

Stage 3: External Works & First Fix (8-12 weeks)

The building becomes watertight, and services begin.

ActivityDuration
Windows and external doors2-3 weeks
Rough electrical (conduits, wiring)3-4 weeks
Rough plumbing (drains, pipes)3-4 weeks
External plastering3-4 weeks

Total: 8-12 weeks (2-3 months)

Stage 4: Second Fix & Finishes (12-16 weeks)

The home takes shape.

ActivityDuration
Internal plastering3-4 weeks
Floor screeds2-3 weeks
Tiling3-4 weeks
Kitchen installation2-3 weeks
Sanitary ware (toilets, basins)2-3 weeks
Painting (internal)3-4 weeks
Light fittings and switches1-2 weeks
Wardrobes and joinery3-4 weeks

Total: 12-16 weeks (3-4 months)

Stage 5: External Finishes (4-8 weeks)

The outside matches the inside.

ActivityDuration
External painting2-3 weeks
Driveways and parking2-3 weeks
Landscaping2-4 weeks
Boundary walls and gates2-3 weeks

Total: 4-8 weeks (1-2 months)


Phase 4: Final Inspections & Handover (4-8 Weeks)

The home is built. Now it must be certified and handed over.

What happens:

  • County final inspection
  • Certificate of Occupation issued
  • Snagging (identifying and fixing minor defects)
  • Client walkthrough and training (systems operation)
  • Final handover and keys

Total: 4-8 weeks


Summary Timeline: 4-Bedroom Custom Home

PhaseDuration
Design & Approvals6 months
Tender & Contractor1 month
Construction15 months
Handover1 month
Total23 months

Just under two years from start to keys.


What Causes Delays?

Design Phase Delays

CauseImpact
Client indecisionWeeks to months
Multiple design changesWeeks
Slow approval process1-3 months extra
Unregistered professionals (drawings rejected)2-4 months

Construction Phase Delays

CauseImpact
Rainy season (especially April-May, October-November)1-2 weeks per heavy rain event
Material shortages2-6 weeks
Late payments to contractorWork stops
Variations (changes during construction)2-8 weeks
Unskilled labour (rework needed)Weeks
Poor site supervisionCumulative delays

The Biggest Delay Factor: Fragmentation

When architect, engineers, and contractor are separate:

  • Design omissions discovered on site require redesign
  • Contractor waits for architect instructions
  • Disputes stop work
  • Client becomes referee

Integrated design-build eliminates most of these delays.


How to Build Faster

1. Decide Before You Design

Every change during construction costs time and money. The more decisions you make during design—finishes, fittings, layouts—the faster construction flows.

Do this: Choose tiles, sanitaryware, kitchen finishes before construction starts, not during.

2. Use an Integrated Team

When design and construction are separate, you build sequentially: design finishes, then tender, then build.

When they’re integrated, design and construction overlap. The team starts site work while detailed drawings continue for upper floors.

Savings: 20-30% faster overall.

3. Pay on Time

Contractors slow down when payments are late. They have other projects waiting. A delayed payment can stop your site for weeks.

Do this: Honor the payment schedule. If cash flow is tight, discuss it early.

4. Order Long-Lead Items Early

Some items take months to arrive:

  • Imported tiles
  • Specialty fixtures
  • Custom joinery (if made off-site)
  • Windows (if manufactured)

Do this: Identify long-lead items during design and order them early.

5. Plan for Rain

Nairobi’s heavy rains (April-May, October-November) can halt excavation and external works.

Do this: Schedule foundation and structure to avoid peak rain months. Plan internal works during rainy periods.


Realistic Expectations: What Clients Don’t Know

“We’ll move in by December”

If you start design in January, you will not move in that December. Construction alone takes 12-18 months.

Reality check: For a December move-in, start design 2 years earlier.

“It’s just a simple house”

Every house is complex. Hundreds of decisions. Thousands of components. Dozens of tradespeople. Simple still takes time.

“The contractor said 8 months”

Contractors often quote optimistic timelines to win jobs. Ask for their last three projects’ actual completion dates vs promised.

“We can design as we build”

This guarantees delays, variations, and stress. Design should be substantially complete before construction starts.


What Real Projects Took

ProjectSizeActual Duration
Maono Residence, Karen450 sqm22 months
Private Villa, Limuru380 sqm19 months
Townhouse, Runda280 sqm16 months
Extension, Lavington120 sqm9 months

All delivered by AFRIK DESIGN & ENGINEERING’s integrated team.


How AFRIK DESIGN & ENGINEERING Delivers on Time

Our integrated model addresses every major cause of delay:

Delay CauseOur Solution
Design omissionsBIM coordination catches clashes before site
Slow approvalsWe manage the entire submission process
Contractor coordinationOne team, one plan
Material delaysEarly ordering, proactive procurement
Rain disruptionSmart scheduling
Late paymentsClear schedules, early communication
Client indecisionGuided decision-making during design

Result: Our projects consistently finish on time—or earlier—with fewer variations and less stress.


Your Realistic Timeline Planner

Use this to plan your project:

MilestoneTarget Date
First architect meeting[ ]
Design complete+4-6 months
Approvals received+2-4 months
Construction starts+1 month
Structure complete+6-8 months
Finishes complete+4-6 months
Handover+2 months
Move in[Total: 19-27 months from start]

Ready to Start?

Building a home is a marathon, not a sprint. But with realistic expectations and the right team, it’s a journey you’ll enjoy—not endure.

Let’s discuss your timeline and how we can deliver your dream home efficiently, beautifully, and on schedule.

Free ConsultationView Our Portfolio


AFRIK DESIGN & ENGINEERING

📞 +254 708 155 714 | +254 731 783 091
📧 info@afrikdesignengineering.com
📍 Limuru Rd, Peak Villa, Ruaka, Kenya

Facebook
Twitter
LinkedIn
Email

Leave a Reply

Your email address will not be published. Required fields are marked *